Budget Variance Analysis
Budget Variance

+₹8.5 L

3.5% over budget
Schedule Variance

+5 days

2% behind schedule
Cost Performance

0.94

Index ratio
Projects At Risk

6

Budget overrun

Budget vs Actual Spending Trend
Variance Distribution

Project-wise Variance Analysis
Project Name Budget Planned Budget Spent Variance Variance % Status Root Cause
Real Estate Portal Revamp ₹45 L ₹42.5 L -₹2.5 L -5.5% Under On Budget Efficient resource usage
Mobile App Development ₹60 L ₹65.8 L +₹5.8 L +9.6% Over Over Budget Scope creep & rework
CRM System Integration ₹35 L ₹36.2 L +₹1.2 L +3.4% Over Monitor Additional testing cycles
Data Analytics Platform ₹52 L ₹50.8 L -₹1.2 L -2.3% Under On Budget Team efficiency